A10, Rush Green

We were hired to carry out a large-scale line marking project within a strict deadline to ensure that any disruption was kept to a minimum for road users. So that the work could be programmed effectively and efficiently, we conducted a thorough pre-start survey to obtain a detailed understanding of the client’s requirements.

Project scope

This was a complex line marking project that was completed in a single night.

Work completed

  • 5,912m of 150mm edge line
  • 1,116m of 150mm centre line
  • 437m of chevron
  • 2 cycle logos
  • 16m of double headed arrows
  • 2 give way triangles
  • 654 road studs

Challenges

In order to ensure that such a large volume of work was completed on time and in accordance with our high standards, we carried out thorough preparatory work in advance. This allowed us to fully understand what was expected of us so that we could put together an effective plan. Drawing on our experience in the industry, we were then able to accurately allocate the workload amongst our team, ensuring that we could maintain consistent progress at all times and avoid disruption. When working within such a tight window, detailed programming is essential for a successful outcome.

Contact Glendining Highways

Call 01708 688 616 or email admin@glendininghighways.com to discuss your project with our expert team. As an experienced highways contractor, we deliver excellence in specialist surfacing throughout the UK.